RIT_Mt_Merrick_MTR_2-6

2021 (Nov/Dec) – Merrick Lodge

Our team focused on the maintenance of the CGL network and preparing it for winter now that construction is completed on all our repeater sites. Apparently, BC winters can get tougher each year. As our crews battled last winter to remove ice from our mountain top infrastructure, we were told that the weather was far…

RIT_Mt_Merrick_MTR_1-3-1

2021 (July/Aug) – Merrick Lodge

Adjustments on the west end of Section 8 required a change to the existing 2-way radio system. Rigstar replaced the Kenwood digital repeater system with a new Motorola SLR5700 Moto TRBO system to accommodate their existing fleet. Service was delivered to the last camp along the Coastal GasLink Pipeline project with the commissioning of Merrick…

RIT_Kitimat_Installation_v1-2

2021 (April/May) – Kitimat, BC

The Main Office in Kitimat was interested in securing a redundant connection. Our team was able to leverage one of our existing sites to deliver a licensed 300Mbps connection to support their operations in the event of a potential network outage. Rigstar coordinated directly with the Network Lead and obtained all the necessary permits and…

Mt_Morice-Rime-1-2-Pine-Marten

2021 (January) – Mount Morice

As we are experiencing one of mildest winters in Calgary, that hasn’t been the case on the mountain-top sites in northern BC. The ice and frost on the towers look amazing but reminds us of how extreme the conditions are and the reason for over-engineering the structures. We have 3 of the 4 sites in…

SCCM 1 - 1-1

2020 (November) – Little Mount Elizabeth

Final preparations of the tower foundation at Little Mount Elizabeth (SCCM-1) were completed in mid-September and required additional engineering. Once completed our team was able to pour the foundation and finish constructing the tower. Currently 2 of the 4 sites are operating at full capacity and the 3rd site requires final alignments and commissioning.

Little-Mt-Elizabeth - 1-3

2020 (August) – Thermal Peak

Scheduling activities was delayed further due to unstable weather (heavy precipitation). The entire month of July, Rigstar managed 4-days of accessibility to Little Mount Elizabeth where we completed the drilling and grouting for the tower foundation. While Little Mount Elizabeth was not able to progress, we scheduled the larger 212 HP helicopter for the shelter…

Corona-Peak-1-1

2020 (June) – Corona Peak Tower

Excellent weather conditions in early May allowed us to have 2 crews working continuously. One crew worked on foundations and structures at Corona Peak while the other continued similar operations at Thermal Peak. Additional excavation of the uneven rock was performed at both sites to reduce the amount of concrete material required to level the…

Mt.Morice_Install_v1-2

2020 (April) – Mt. Morice

Early April, amidst the uncertainty of a world-wide pandemic, investigation of the other 3 tower sites began. The entire project team came together and following all protocols, mitigated the risks to an acceptable level for everyone involved. The crew found 2 sites that were mostly wind-blown and accessible to begin work, while the 3rd site,…

Parsnip - January 2020

2020 (January) – Parsnip

Rigstar implemented a Long-Haul Cellular service solution to the Parsnip Camp and upgraded the Microwave Wireless Data capacity into the camp from 300Mbps to 1Gbps. Rigstar had to access a mountain top repeater tower to install cellular and microwave gear via a 14km Snowmobile only access trail. Our team was able to complete the install…