2020 (August) – Thermal Peak

Scheduling activities was delayed further due to unstable weather (heavy precipitation). The entire month of July, Rigstar managed 4-days of accessibility to Little Mount Elizabeth where we completed the drilling and grouting for the tower foundation.
While Little Mount Elizabeth was not able to progress, we scheduled the larger 212 HP helicopter for the shelter lifts at Thermal Peak & Corona Peak. We planned both lifts for one day, as the larger helicopter availability was not always local to the area. Both shelters were long lined and set in place on August 10, 2020.