2020 (June) – Corona Peak Tower

Excellent weather conditions in early May allowed us to have 2 crews working continuously. One crew worked on foundations and structures at Corona Peak while the other continued similar operations at Thermal Peak. Additional excavation of the uneven rock was performed at both sites to reduce the amount of concrete material required to level the tower footings.
Corona Peak tower was erected May 10, 2020 with completion of the shelter pad by May 12th. The tower installation at Thermal Peak was completed May 12, followed by more inclement weather.