2020 (April) – Mt. Morice

Early April, amidst the uncertainty of a world-wide pandemic, investigation of the other 3 tower sites began. The entire project team came together and following all protocols, mitigated the risks to an acceptable level for everyone involved. The crew found 2 sites that were mostly wind-blown and accessible to begin work, while the 3rd site, nearest to Kitimat was still under 1.5 meters of snow. April 8th, survey of the first site on Thermal Peak, overlooking P4 site and west side of Icy Pass, was completed and pins were installed defining all anchor points for the tower foundation as well as the shelter platform foundation. On the same day, survey was completed for the site on Corona Peak, overlooking P2 site.